Planning CLC block installation: joints, bond and finishes

Use the approved CELBLOC guidance to coordinate the first course, jointing system, block overlap and interfaces before work starts.

The idea, illustrated

A half-length offset changes with the unit.

600 mm unit

300 mm

450 mm unit

225 mm
Horizontal geometry only; not a wall design. Archived guidance calls for at least 250 mm overlap. A 450 mm half-length offset is 225 mm and needs an approved alternative bond detail.

Start with the approved wall detail

CELBLOC is described in the current datasheet for non-load-bearing walls and partitions above plinth. Installation planning should therefore identify what supports the wall and what restrains it. Do not treat the wall as an unconnected stack of units, or assume that a photograph provides a construction detail. [source]

Before material reaches the workface, coordinate wall height and thickness, frame connections, opening heads, service routes, movement accommodation and finishes. Record who approves each interface. This guide is a planning sequence; the responsible designer's project details govern construction.

Choose one compatible jointing system

The approved R03 sheet records archived manual guidance of approximately 8–10 mm conventional mortar joints or 3–4 mm thin-bed joints. It also calls for filled bed and head joints. These are archived guidance values, not permission to substitute any mortar or adhesive available on site. [source]

Agree the compatible product, joint thickness, preparation, mixing instructions and application method. Confirm how dimensional variation is handled and how the first course is established. A thin-bed system should not be used to conceal an unresolved levelling or tolerance problem.

A practical trial panel should use the proposed jointing and finish materials. Inspect joint filling, alignment, cutting quality and interfaces before repeating the method across the project. Record the accepted materials so subsequent deliveries do not silently change the system.

Resolve the 450 mm overlap question

The archived manual cited in R03 gives a minimum overlap of 250 mm. Half of a 600 mm block is 300 mm, while half of a 450 mm block is 225 mm. Consequently, a simple half-bond layout for a 450 mm unit does not meet that archived figure.

The correct response is to obtain an approved bond detail for the chosen product and wall. Do not silently relax the figure, invent a cut pattern, or conclude that every 450 mm wall is unsuitable. The diagram shows the dimensional conflict so the designer and supplier can resolve it explicitly.

A 600 mm half-length exceeds 250 mm geometrically, but this alone is not approval of a complete wall. Corners, junctions, end conditions and openings still require coordination.

Keep services and finishes in the same plan

Mark the positions of service penetrations and attachments before blockwork begins. Agree the permitted cutting and chasing method with the project team. Heavy attachments, deep chases or changes to the proposed wall should be referred for design review instead of being improvised after the wall is finished.

For plaster or render, identify the compatible system, substrate preparation and treatment at material transitions. Use the finish supplier's instructions and the approved project detail. An AAC-specific fixing or render recommendation is not automatically a CELBLOC instruction.

Plan unloading, a stable storage area, protected handling and cutting controls. Use the selected equipment's instructions and the site's safety arrangements, including suitable dust control. Avoid transferring damaged or unverified units into an approved sample wall without review.

Use a hold-point record

Example workmanship review points
Before proceedingWhat the team should record
First courseSet-out, support, level and selected jointing system.
Typical wall bayBond, filled joints, alignment, restraints and openings.
Services and finishesApproved penetrations, attachments, preparation and interface treatment.
HandoverDrawing revision, materials used and any accepted deviations.

The source manual's revision dates remain unconfirmed, as stated in R03. Use the archive to ask the right technical questions, then resolve them in current approved project documents.

Sources & scope

Primary references consulted for this guide. Worked examples are illustrative. Apply the project specification and the appropriate adopted test methods.

  1. SEED Materials · CELBLOC technical datasheet R03, 25 October 2026

    Approved dimensions, application limits and archived installation guidance; archive revision dates unconfirmed.